MOS Mask Milling Machine Issue

Apr 10, 2025

April 9, 2025: The laser for the MOS mask milling machine recently stopped working.  Currently all mask milling for LUCI and MODS is halted while the issue is resolved.

Read Now

LUCI1 Filter Wheel#2 (Broadband) Switch Issue

Apr 03, 2025

Apr 2, 2025: Flaky switch on LUCI1 Filter Wheel #2 (broadband filters).
LUCI1’s Filter Wheel #2, where the broadband filters are located, is showing a flaky position sensing switch that affects all higher-numbered filters, which includes all but the zJspec …

Read Now

LUCI1 Critical MOS error Recovery Status

Mar 09, 2025

Mar 13, 2025: All normal modes with LUCI1 are released for science.
N375 and N30 imaging, as well as G210 and G200 spectroscopic modes have all been released for normal science use.
 
Mar 9, 2025: LUCI1 All modes **NOT** …

Read Now

SX ASM Status Update

Feb 14, 2025

Update Feb 24, 2025
On-sky seeing limited checkouts were completed on UTFeb24.  The binodal astigmatism was measured and collimation tables updated.  The SX ASM is released for all available seeing-limited science modes without restrictions.
 
Update Feb 14, 2025
ASM …

Read Now

DX AO in Cold Conditions

Jan 21, 2025

DX ASM in Cold Weather Update – Jan 21, 2025
Work was done in summer shutdown 2024 to attempt to address the issues causing the failures in cold temperatures with the DX ASM.  Unfortunately, we have continued to see the …

Read Now

DX LUCI AO FW issue – Shared Risk Release

Jan 11, 2025

Jan 09, 2025
The DX LUCI WFS experienced an issue with one of the filter wheels.  This filter wheel is used for very bright targets only with an R magnitude brighter than 8th magnitude.  LUCI full AO and LUCI ESM …

Read Now

LBTI Instrument Status

Sep 10, 2024

As of Sept. 9, 2024, LBTI’s camera cryostat (NIC) remains off the telescope for ongoing maintenance and upgrade work, with some major uncertainty on the observing modes that will be available for 2024B and 2025A.  PIs of accepted 2024B programs …

Read Now

LBTO Restart 2024

Aug 30, 2024

Summer Shutdown 2024 Wraps up on Aug 30, 2024 with the first on-sky checkout of our instruments taking place Aug 30 weather permitting.
Update Sept 2 2024: On UT Sept 1 the Telescope experienced a water intrusion event.  The SX …

Read Now

LUCI2: Displaced G200 Spectra (LUCI2 G200 available)

Jun 28, 2024

LUCI2 G200 Available – problem understood!  (June 28, 2024)
The G200 tilt issue is now understood.  The “in position” switches turn on just before the grating wheel engages the detent.  With a few dropped steps this can leave the grating …

Read Now

DX Adsec to be removed

Jun 11, 2024

DX Adsec Removed – June 12, 2024
DX Adsec will be removed before SSD24 to address a potential issues with a board in crate3. The rigid secondary will be installed for the remainder of the semester. The unit has maintenance …